Description

On behalf of BKB Infra, the Roos Groep carried out the work. Over 1 kilometre of cycle path in Ittervoort (NL) only 12 cm thick with 2,0 kg per m³ concrete of our newest fibre the Concrix Superfloor. The concrete mix produced and supplied by Betoncentrale Raijmakers has a low MKI due to the use of 100% granulate. This in combination with 4 cm less concrete thickness (140 m³ less concrete) in the cycle path contributes to a reduction in CO₂ emissions while maintaining the same end result.

Advantages of Concrix SuperFloor Solution:

  • Cost reduction (material and labour)
  • No corrosion – longer service life
  • Less CO₂ – environmentally friendlier (EPD certified)
  • No visible fibres on the surface – broom finish
  • Massive reduction of early shrinkage cracks

Application Infrastructure cycle path
Object
Low load external area
Size 1 000 m
Country The Netherlands
Year 2023
Fibre Concrix SuperFloor 2.0 kg/m³