Hydro Power Plant Station «Berschnerbach»,
Berschis (CH)
Projects
Description
The tunnel for the pressure water pipe of the hydro power plant station «Berschnerbach» (≈ 1300 m length) with a gradient from 20% (pipe gallery) up to 142% for the inclined shaft. The permanent inner lining sprayed concrete is only reinforced with the synthetic high-performance fibre Concrix ES.
Advantages of Concrix ES Solution:
- Cost savings (no steel mounting, lower logistic costs, shorter construction time)
- High performance (700 Joule after only 7 days – EN 14488-5)
- No corrosion and thus lower future maintenance cost
- Non-creeping-tested and durability tested fibre
Application Shotcrete tunnel
Object Tunnel for pressure water pipe
Client Kraftwerk Berschnerbach AG
Company Gasser Felstechnik AG
Country Switzerland
Year 2018
Fibre Concrix ES – 4,5 kg/m³